Sable Offshore Corp. Provides Operational Update
Sable Offshore completed reconstruction and internal commissioning of Platform Hondo and expects final Marine Minerals Administration approval in October 2026, with a Q4 2026 platform restart targeted. The company accelerated 4 additional Perforation Adds, expecting 9 of 15 production wells completed before restart versus 5 previously planned; each Perf Add adds ~600 bopd at roughly $800,000 per operation. LFC upgrades are planned so the midstream facility can handle full capacity from all three SYU platforms; it currently processes about 80% of Harmony and Heritage output.
Key figures
- Perf add cost
- approximately $800,000 per operation
- Restart timing
- expected Q4 2026
- Jul aug oil sales
- approximately 32 thousand gross barrels of oil per day
- October exit rate
- approximately 45 thousand gross barrels of oil per day
- Perf adds planned
- 4
- October nominations
- average of 38 thousand gross barrels of oil per day
- September oil sales
- approximately 34 thousand gross barrels of oil per day
- Lfc current processing
- approximately 80% of productive capacity of Platforms Harmony and Heritage
- Perf add incremental production
- ~600 barrels of oil per day
- Perf adds completed pre restart
- 9 of 15 production wells