RenX Enterprises Sets Microtec Turbo Mill in Place at Myakka City; Engineered Substrate Commissioning Remains on Track for Fourth Quarter of 2026

$RENXPress releaseSep 30, 2026, 7:30 AM ETRead the release

RenX set its Microtec UTM 1200 Turbo Mill onto its anchored support stand at the Myakka City, Florida facility, completing the fourth of seven installation milestones. Commissioning remains on track for Q4 2026, aided by early funding of contractor and utility scopes that prepared the site before the mill arrived from Germany in August.

Key figures

Revenue
$15.0 million
Guidance
Engineered substrate commissioning remains on track for Q4 2026
Revenue Yoy
0
Ttm revenue
$15.0 million
Facility acres
80+
Record quarterly revenue
$4.26 million
Installation milestones total
7
Installation milestones completed
4