IREN Announces First Australian Data Center Campus - 800MW in South Australia
IREN signed a transmission connection agreement for an 800MW data center campus in Bundey, South Australia, marking its first announced project in the country. The site secures four 330kV feeder exits at a utility substation, supporting the full capacity without requiring network upgrades, with energization targeted for 2028.
Key figures
- Voltage k v
- 330
- Capacity mw
- 800
- Ongoing jobs
- 200
- Construction jobs
- 500
- Energization year
- 2028