TeraWulf Expands Contracted Power Capacity at its Muskie Data Campus to 1 GW

$WULFPress releaseOct 5, 2026, 8:15 AM ET

TeraWulf executed an amended electric service agreement with Kentucky Power that doubles contracted power at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The amendment pulls forward planned delivery of Muskie's second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval, with the first 500 MW phase still targeted to begin ramping in 2028.

Key figures

Campus potential
up to 2 GW
Phase 2 delivery
2029 (pulled forward from 2030)
Phase 1 ramp target
2028
Prior contracted power
500 MW
Total contracted power
1 GW