Integra Provides DeLamar Project Update: Detailed Engineering, Permitting, Procurement and State of Good Repairs Work Advancing in Line with Plan, Appoints GenCap as Project Financing Advisor
Integra Resources provided an update on the DeLamar Gold-Silver Project, confirming detailed engineering, procurement, permitting, and state-of-good-repair work are advancing in line with plan toward a Final Investment Decision expected after the EIS and Record of Decision in the second half of 2027. The company appointed GenCap Mining Advisory as project financing advisor to structure capital alternatives well ahead of FID, and expects principal long-lead equipment purchases (Merrill-Crowe plant, crushing facility, electrical equipment) to be ordered by end of 2026.
Key figures
- Fid timing
- second half of 2027
- After tax irr
- 46%
- After tax npv
- US$774 million
- Initial capital
- US$389 million
- Base case gold price
- US$3,000 per ounce
- Pilot tons processed
- approximately 39,000 tons
- Lom annual production
- 106,000 gold-equivalent ounces
- Base case silver price
- US$35 per ounce
- Power capacity by 2030
- approximately 6 megawatts
- Annual production years 1 5
- approximately 119,000 gold-equivalent ounces