Digi Power X Announces $200 Million Debt Financing Commitment to Support Completion of Alabama AI Data Center and Provides Expansion Update

$DGXXPress releaseOct 13, 2026, 7:30 AM ETRead the release

Digi Power X received a commitment letter for US$200 million in project-level debt financing, syndicated by Goldman Sachs, to complete its 40 MW AI data center in Columbiana, Alabama. The financing is expected to close within 90 days, subject to definitive documentation and lender diligence, and proceeds preserve corporate liquidity and avoid further shareholder dilution; no shares were issued under the ATM program in Q3 2026. Construction remains on schedule with Phase 1 due in December 2026 and Phase 2 in March 2027, while the first ARMS 200 modular unit has operated since May 2026 supporting GPU bare-metal services with Supermicro.

Key figures

Deal Value Usd
200000000
Cash position
135000000
Capex ytd 2026
153000000
Phase1 completion
December 2026
Phase2 completion
March 2027
Alabama capacity mw
40