Skip to main content
Signal8

NANO Nuclear’s KRONOS MMR™ Program Advancing Through U.S. NRC Review with the University of Illinois Urbana-Champaign

$NNEPress releaseOct 13, 2026, 8:30 AM ETRead the release

NANO Nuclear and the University of Illinois Urbana-Champaign are advancing through the NRC's audit and technical review of the KRONOS MMR Construction Permit Application, which was formally accepted for review in May 2026. The NRC's public schedule targets a draft Environmental Assessment and Safety Evaluation in February 2027, a final Environmental Assessment in May 2027, and a final Safety Evaluation in September 2027.

Key figures

Cpa submitted
March 31, 2026
Construction target
second half of 2027
Nrc formal acceptance
May 18, 2026
Final safety evaluation
September 2027
Draft ea and safety eval
February 2027
Final environmental assessment
May 2027

AI analysis

Red flags1 · Pro

The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.

AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.