i-80 Gold Provides a Development Update; Archimedes Underground and Lone Tree Plant Refurbishment Remain on Track and Mineral Point Open Pit Prioritized in Updated Development Plan
i-80 Gold reported that its Nevada development plan remains on track, with Archimedes underground set to begin production mining in Q4 2026 and the Lone Tree Plant refurbishment advancing on schedule toward first gold pour in Q4 2027. Capital discipline is holding: the $430 million Lone Tree cost estimate remains largely intact with roughly 10% of contingency drawn, though labor costs are running 5-10% above initial estimates, and the company is prioritizing the Mineral Point open pit — its most valuable asset, with potential to add approximately 280,000 gold equivalent ounces annually over a 17-year mine life — ahead of the Granite Creek open pit.
Key figures
- Labor cost overrun
- 5% to 10% above initial estimates
- Capex 2026 guidance
- $140 million to $160 million
- Capital committed pct
- approximately 44%
- Lone tree throughput tpd
- approximately 2,250
- Production target 2028 oz
- 150,000 to 200,000
- Production target 2031 oz
- 400,000 to 500,000
- Broader plan production oz
- 500,000 to 600,000
- Mineral point mine life years
- 17
- Processing margin gain per oz
- $1,000 to $1,500
- Granite creek m and i increase
- approximately 230%
- Lone tree capital cost estimate
- $430 million
- Procurement packages awarded pct
- approximately 74%
- Mineral point annual production geoz
- approximately 280,000