Sunshine Silver Mining & Refining Advances Operational Readiness at the Sunshine Mine

$SSMRPress releaseOct 19, 2026, 6:30 AM ETRead the release

Sunshine Silver Mining reported continued operational-readiness progress at the Sunshine Mine, targeting feasibility-study completion in Q2 2027 and a return to production in late 2028. The company has completed roughly 47,600 of 50,000 meters of underground infill drilling, advanced 1,200 meters of underground development in H1 2026 with 1,300 more planned for H2, and commissioned a new production hoist on the Jewell Shaft.

Key figures

Jewell shaft depth feet
4000
Feasibility study target
Q2 2027
New rail installed meters
1200
Production restart target
late 2028
Future throughput capacity tpd
2000
Infill drilling program meters
50000
Silver summit shaft depth feet
5400
Mobile equipment units acquired
20
Initial processing throughput tpd
1000
New rail planned by year end meters
1900
Underground development h1 2026 meters
1200
Infill drilling completed sept 30 2026 meters
47600
Underground development h2 2026 planned meters
1300
Underground development completed sept 30 2026 meters
700