Sunshine Silver Mining & Refining Advances Operational Readiness at the Sunshine Mine
Sunshine Silver Mining reported continued operational-readiness progress at the Sunshine Mine, targeting feasibility-study completion in Q2 2027 and a return to production in late 2028. The company has completed roughly 47,600 of 50,000 meters of underground infill drilling, advanced 1,200 meters of underground development in H1 2026 with 1,300 more planned for H2, and commissioned a new production hoist on the Jewell Shaft.
Key figures
- Jewell shaft depth feet
- 4000
- Feasibility study target
- Q2 2027
- New rail installed meters
- 1200
- Production restart target
- late 2028
- Future throughput capacity tpd
- 2000
- Infill drilling program meters
- 50000
- Silver summit shaft depth feet
- 5400
- Mobile equipment units acquired
- 20
- Initial processing throughput tpd
- 1000
- New rail planned by year end meters
- 1900
- Underground development h1 2026 meters
- 1200
- Infill drilling completed sept 30 2026 meters
- 47600
- Underground development h2 2026 planned meters
- 1300
- Underground development completed sept 30 2026 meters
- 700