Valor Energy Inc. Enters into Agreement to Acquire 18MW Computing Center in Youngstown, Ohio
Valor Energy signed an agreement to acquire 100% of the entity holding an 18MW operational computing center in Youngstown, Ohio, for an aggregate purchase price of $3.6 million. The ~30,888 square-foot site has 18 MVA of apparent power capacity under an existing, believed-energized 23kV Ohio Edison interconnection, which the company says could shorten its path to deploying AI computing capacity versus building on undeveloped land. Closing is subject to a 30-business-day due diligence period, third-party and regulatory consents, and is expected no later than the 90th business day after the effective date; Valor retains a unilateral termination right during diligence.
Key figures
- Deal Value Usd
- 3600000
- Facility sqft
- 30888
- Power capacity
- 18 MVA apparent power under existing 23kV Ohio Edison interconnection
- Expected closing
- no later than the 90th business day following the effective date
- Due diligence period
- 30 business days
AI analysis
The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.
AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.