Namib Minerals Announces Expanded Milling Plant at How Mine Operating at Full Capacity, Ahead of Schedule

$NAMMPress releaseOct 26, 2026, 9:00 AM ETRead the release

Namib Minerals' expanded milling plant at How Mine is commissioned and operating at its full rate of approximately 55,000 tonnes per month, well ahead of the six-to-eight-week ramp-up and end-of-December target. The expansion lifts processing capacity about 36% from roughly 40,500 tonnes per month and is expected to relieve the milling bottleneck that had limited throughput, spreading the existing cost base over greater volumes.

Key figures

Capacity increase pct
36%
Full rate target original
end of December 2026
Ramp up timeline original
six to eight weeks
Milling capacity tonnes per month new
55000
Milling capacity tonnes per month prior
40500