Waste Energy Completes Fifth and Final Crane Day as WE #1 Enters Final Stage of Buildout

$WASTPress releaseOct 26, 2026, 9:22 AM ETRead the release

Waste Energy Corp. completed its fifth and final major crane day at the Midland, Texas campus, putting the WE #1 waste conversion system at approximately 85-90% completion. The company is targeting December 1, 2026 for WE #1 to be fully operational, with remaining work focused on connections, piping, testing and commissioning.

Key figures

Midland acres
12.5 acres
Shop space sqft
12500
Prior midland acres
4 acres
Buildout complete pct
85-90%
Operational target date
December 1, 2026