Osisko Gold Provides Construction Progress Update on the Cariboo Gold Project

$OGGPress releaseOct 27, 2026, 7:00 AM ETRead the release

Osisko Gold provided a construction update on its 100%-owned Cariboo Gold Project, now estimated at approximately 28% complete with first gold pour targeted for Q1 2029 and commercial production in H2 2029. Cumulative costs reached CAD $355 million through September 30, 2026, with an estimated CAD $907 million remaining to complete construction; detailed engineering is ~42% complete and over 50% of procurement packages are awarded.

Key figures

Trifr
1.05
On site workforce
400
Equipment fleet value
43000000
Procurement committed
360000000
Project completion pct
28
Drilling planned meters
160000
Detailed engineering pct
42
Underground developed km
3.4
Cumulative costs incurred
355000000
Remaining cost to complete
907000000
Procurement packages awarded
over 50%
Underground advance rate target
360 metres per month by year-end 2026 (revised from 500)