Ximen Mining Corp. Provides Kenville Site Update and Targets Early November Portal-Face Start
Ximen Mining reported that site infrastructure, power, equipment, and a startup crew are in place at the Kenville Gold Mine, with portal-face work now targeted for early November 2026. The start slipped from the prior end-of-October target, mainly to complete remaining permit preconditions including explosives storage and use authorization; the company expects all requirements in place within two weeks.
Key figures
- Original target
- end of October 2026
- Financing status
- non-dilutive/development funding discussions continuing; no definitive agreement
- Portal start target
- early November 2026