NextDecade Provides Third Quarter 2026 Business Update

$NEXTPress releaseOct 29, 2026, 8:00 AM ETRead the release

NextDecade reported strong Q3 2026 progress on Rio Grande LNG, with Phase 1 construction on budget and ahead of schedule -- first LNG from Train 1 is now expected in Q2 2027, a quarter ahead of the guaranteed EPC schedule with Bechtel. Regulatory wins stacked up: the USACE authorized Train 6 in record time, and FERC approved an uprate of Trains 1-5 capacity from 27 MTPA to 30.15 MTPA; the company also plans to pre-file with FERC for Trains 7-8 before year-end. Management projects implied margins on uncontracted volumes above $6 per MMBtu, more than $1 above base case guidance, citing strong spot LNG prices from lost Middle East supply.

Key figures

Notes tranches
["$1.0B due 2031 at 5.25%","$500M due 2034 at 5.50%","$1.25B due 2036 at 5.75%","$750M due 2041 at 6.15%"]
Train6 fid target
second half of 2027
Authorized capacity
30.15 MTPA (Trains 1-5, up from 27 MTPA after FERC uprate)
First lng production
Q2 2027 (Train 1), a quarter ahead of guaranteed EPC schedule
Phase1 equity interest
20.8% of distributions
Train4 equity interest
40% (rises to 60%)
Train5 equity interest
50% (rises to 70%)
Swap settlement receipts
109.2 million
Implied margin uncontracted
over $6 per MMBtu, more than $1 per MMBtu above base case guidance