NextDecade Provides Third Quarter 2026 Business Update
NextDecade reported strong Q3 2026 progress on Rio Grande LNG, with Phase 1 construction on budget and ahead of schedule -- first LNG from Train 1 is now expected in Q2 2027, a quarter ahead of the guaranteed EPC schedule with Bechtel. Regulatory wins stacked up: the USACE authorized Train 6 in record time, and FERC approved an uprate of Trains 1-5 capacity from 27 MTPA to 30.15 MTPA; the company also plans to pre-file with FERC for Trains 7-8 before year-end. Management projects implied margins on uncontracted volumes above $6 per MMBtu, more than $1 above base case guidance, citing strong spot LNG prices from lost Middle East supply.
Key figures
- Notes tranches
- ["$1.0B due 2031 at 5.25%","$500M due 2034 at 5.50%","$1.25B due 2036 at 5.75%","$750M due 2041 at 6.15%"]
- Train6 fid target
- second half of 2027
- Authorized capacity
- 30.15 MTPA (Trains 1-5, up from 27 MTPA after FERC uprate)
- First lng production
- Q2 2027 (Train 1), a quarter ahead of guaranteed EPC schedule
- Phase1 equity interest
- 20.8% of distributions
- Train4 equity interest
- 40% (rises to 60%)
- Train5 equity interest
- 50% (rises to 70%)
- Swap settlement receipts
- 109.2 million
- Implied margin uncontracted
- over $6 per MMBtu, more than $1 per MMBtu above base case guidance