Potomac Edison Advances Power Line Upgrades to Strengthen Reliability for Virginia Customers

$FEPress releaseNov 2, 2026, 11:33 AM ETRead the release

Potomac Edison, a FirstEnergy subsidiary, filed with Virginia's State Corporation Commission on Oct. 30, 2026 for its Gore-Doubs-Goose Creek transmission upgrade, seeking a Certificate of Public Convenience and Necessity. The project rebuilds roughly 29 miles of 138 kV lines across Frederick, Clarke and Loudoun counties, mostly along existing routes, with construction targeted for 2028 and a Virginia in-service date of December 2030.

Key figures

Construction start
2028
Va in service date
December 2030
Firstenergy customers
more than six million
Miles of 138kv rebuild
29
Capital investment plan
$36 billion
Transmission line miles
24,000
Potomac edison customers md
285,000
Potomac edison customers wv
155,000