Fermi disclosed that the Data Center Lease and Services Agreement with TensorWave TEX1 did not become effective by its October 31, 2026 closing date. The company says both parties remain committed, no termination rights have been exercised, and outstanding conditions include work letters, guaranties, board approvals, and project-level construction financing.
Key figures
- Lease signed
- August 2026
- Lease status
- not yet effective; closing conditions unsatisfied
- Original closing date
- October 31, 2026