Silvercorp Announces Project Update for El Domo
Silvercorp raised the El Domo construction budget to $298.2 million, up $14.6 million from the February 2026 estimate of $283.6 million and well above the 2021 feasibility-study figure of $248 million. Cost drivers include Ecuador's elimination of diesel subsidies ($8.3M), enhanced water-management infrastructure ($4.7M), and added power-supply and processing-plant items, partly offset by $9.8 million in savings.
Key figures
- Guidance
- El Domo now scheduled to be in production by November 1, 2027 (4-month delay)
- Delay months
- 4
- Prior budget musd
- 283.6
- Updated budget musd
- 298.2
- Budget increase musd
- 14.6
- Remaining budget musd
- 213.6
- Actual spend sep30 2026 musd
- 84.6
- Feasibility 2021 budget musd
- 248