Silvercorp Announces Project Update for El Domo

$SVMPress releaseNov 3, 2026, 5:05 PM ETRead the release

Silvercorp raised the El Domo construction budget to $298.2 million, up $14.6 million from the February 2026 estimate of $283.6 million and well above the 2021 feasibility-study figure of $248 million. Cost drivers include Ecuador's elimination of diesel subsidies ($8.3M), enhanced water-management infrastructure ($4.7M), and added power-supply and processing-plant items, partly offset by $9.8 million in savings.

Key figures

Guidance
El Domo now scheduled to be in production by November 1, 2027 (4-month delay)
Delay months
4
Prior budget musd
283.6
Updated budget musd
298.2
Budget increase musd
14.6
Remaining budget musd
213.6
Actual spend sep30 2026 musd
84.6
Feasibility 2021 budget musd
248