Silvercorp raised the El Domo construction budget to $298.2 million, a net increase of $14.6 million versus the $283.6 million estimate from February 2026, citing diesel subsidy elimination in Ecuador, water management enhancements, and plant construction refinements. The completion schedule is now expected to slip four months due to extended Super El Nino rainfall, with first production at El Domo targeted for November 2027, subject to weather and contractor performance.

Key figures

Prior budget usd m
283.6
Targeted production
November 2027
Budget increase usd m
14.6
Remaining budget usd m
207.3
Production delay months
4
Mining contract value usd m
35
Offsetting reductions usd m
9.8
Feasibility 2021 budget usd m
248
Spent as of sep 30 2026 usd m
90.9
Remaining owner contingency usd m
14.3
Updated construction budget usd m
298.2