Salazar Resources' 25% El Domo Interest Remains Fully Carried Through Updated US$298 Million Construction Budget
Silvercorp, as operator of the Curipamba-El Domo copper-gold project, raised the construction budget 5% to US$298.2 million and pushed the first production target back four months to November 2027, citing extended Super El Niño rainfall and the elimination of Ecuador's diesel subsidy. Silvercorp has funded US$90.9 million of construction to date, with US$207.3 million remaining under the updated budget, which retains US$14.3 million of owners' contingency after a US$2.7 million reduction. Construction of the external power line is delayed pending CNEL reviews and approvals, and continued delays would force longer reliance on 17 MW of generator sets, potentially raising operating costs.
Key figures
- Deal Value Usd
- 0
- Production target
- November 2027
- Vat in budget usd m
- 36.7
- Budget increase usd m
- 14.6
- Generator capacity mw
- 17
- Schedule delay months
- 4
- Remaining budget usd m
- 207.3
- Owners contingency usd m
- 14.3
- Spent to sep 30 2026 usd m
- 90.9
- Mining contract value usd m
- 35
- Prior budget feb 2026 usd m
- 283.6
- Silvercorp project interest
- 75%
- Updated construction budget usd m
- 298.2
AI analysis
The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.
AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.