Willdan to Provide Engineering for 643 MW in Energy Infrastructure Projects
Willdan Group received limited notices to proceed for engineering and procurement on substation and battery energy storage projects totaling 643 MW of capacity. The project mix includes a transformer substation for a 100 MW datacenter in California plus renewables substations and a 75 MW BESS across Texas and Illinois, reflecting demand tied to datacenter buildout and grid constraints.
Key figures
- Projects
- ["100 MW datacenter transformer substation in CA","75 MW BESS in TX","300 MW renewables transformer substation in TX","88 MW renewables transformer substation in IL","80 MW renewables transformer substation in IL"]
- Capacity mw
- 643
AI analysis
Red flags2 · Pro
The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.
AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.