Contracted Capacity, Containers on the Water: AZIO AI Moves Atlas One Into Its Equipment Phase

$AZIOPress releaseNov 6, 2026, 11:36 AM ET

AZIO AI says its Atlas One AI compute campus has entered the equipment phase, with shipping containers in transit and a phased build coordinated with site partner Texoil Ventures LLC. The only signed customer contract remains the 10 MW Power Champion hosting agreement at $150 per kW per month — $1.5 million per month and roughly $90 million over the 60-month term at full delivery, plus energy billed at $0.13 per kWh. No capacity has been energized and these figures are contracted economics, not recognized revenue.

Key figures

Energy rate per kwh
$0.13 per kWh
Expansion rights mw
50
Phase one planned mw
11
Contracted capacity mw
10
Contract value 60 months
$90 million
Capacity rate per kw month
$150 per kW per month
Targeted rate other clients
$255 per kW per month
Phase one progress target mw
6
Long term capacity objective mw
500
Monthly revenue at full delivery
$1.5 million per month