Lithium Americas' definitive capex estimate for Thacker Pass Phase 1 rose to $3.83 billion from $2.93 billion, a roughly $900 million increase driven by labor costs, tariffs, logistics and added contingency. Mechanical completion remains on track for late 2027 with commercial production in 2028, and the ~$995 million incremental funding requirement is expected to be covered by $650 million in company contributions to the JV plus $315 million of DOE loan reserve funding. 2026 capex guidance was raised to $1.7-$2.0 billion, and the company reported ~$1.3 billion in cash and restricted cash as of September 30, with Q3 results due November 12.
Key figures
- Guidance
- FY2026 capex guidance raised to $1.7B-$2.0B from $1.3B-$1.6B for Thacker Pass Phase 1
- Production capacity
- 40,000 tonnes/year lithium carbonate
- Prior capex estimate
- $2.93 billion
- Commercial production
- 2028
- Mechanical completion
- late 2027
- Updated capex estimate
- $3.83 billion
- Cash and restricted cash
- $1.3 billion (Sept 30, 2026)
- Doe loan cumulative advances
- $1.448 billion
- Incremental funding requirement
- $995 million