Lithium Americas Provides Thacker Pass Project Update

$LACPress releaseNov 11, 2026, 6:55 AM ETRead the release

Lithium Americas' definitive capex estimate for Thacker Pass Phase 1 rose to $3.83 billion from $2.93 billion, a roughly $900 million increase driven by labor costs, tariffs, logistics and added contingency. Mechanical completion remains on track for late 2027 with commercial production in 2028, and the ~$995 million incremental funding requirement is expected to be covered by $650 million in company contributions to the JV plus $315 million of DOE loan reserve funding. 2026 capex guidance was raised to $1.7-$2.0 billion, and the company reported ~$1.3 billion in cash and restricted cash as of September 30, with Q3 results due November 12.

Key figures

Guidance
FY2026 capex guidance raised to $1.7B-$2.0B from $1.3B-$1.6B for Thacker Pass Phase 1
Production capacity
40,000 tonnes/year lithium carbonate
Prior capex estimate
$2.93 billion
Commercial production
2028
Mechanical completion
late 2027
Updated capex estimate
$3.83 billion
Cash and restricted cash
$1.3 billion (Sept 30, 2026)
Doe loan cumulative advances
$1.448 billion
Incremental funding requirement
$995 million