TC Energy outlined the next phase of growth on its NGTL System, including the proposed Alberta Growth Connector, a roughly 370-kilometre, 48-inch pipeline linking Western Canadian gas supply to Alberta's oil sands region. The 2026 NGTL Annual Plan forecasts system demand rising about 25% over five years, from 14.4 Bcf/d in 2026 to roughly 18 Bcf/d in 2031, with more than 60% of the increase from oil sands, power generation and data centres. The Alberta Growth Connector would initially add about 1 Bcf/d of capacity, and additional service offerings launching as early as January 2027 could exceed 1.3 Bcf/d of new delivery service between 2030 and 2032.

Key figures

Ngtl rate base
nearly $19 billion
Ngtl invested decade
$15 billion
Demand growth forecast
approximately 25% over five years (2026-2031)
Ngtl demand 2026 bcf d
14.4
Ngtl demand 2031 bcf d
18
Sanctioned ngtl projects
$1.2 billion
Alberta growth connector length km
370
New delivery service potential bcf d
1.3
Alberta growth connector initial capacity bcf d
1