AIB Data Centers Reports Third Quarter 2026 Results, Highlighted by 12-Year Customer Agreement and Nearly Doubled Contracted Power

$AIBPress releaseNov 16, 2026, 4:05 PM ETRead the release

AIB Data Centers reported Q3 2026 revenue of $0.8 million, down from $4.2 million a year ago, with a net loss of $4.8 million ($0.06 per share) as the legacy hosting site sits de-energized for redevelopment into CLT1. The quarter's headline was a 12-year Master Colocation Services Agreement with Nebius for 50 MW at CLT1, backed by a parent guarantee, and contracted utility power roughly doubled to approximately 120 MW following the DFW1 acquisition. Prepayments are funded into escrow and AIB has received its first draw, with the first 25 MW data hall targeted for Q4 2027.

Key figures

Revenue
813,229
Guidance
First 25 MW data hall at CLT1 targeted for Q4 2027; second in Q1 2028; revenue to begin as each hall commences operations
Revenue YoY
-81%
Clt1 esa mw
65
Total assets
91,448,256
Dfw2 pipeline mw
60
Gso1 pipeline mw
90
Nine month revenue
8,641,890
Contracted power mw
120
Nebius agreement mw
50
Stockholders equity
78,212,576
Dfw1 acquisition cost
11,608,419
Nebius agreement years
12
Cash and restricted cash
25,501,193
June 2026 offering net proceeds
58,970,837