FingerMotion Completes Design Basis Memorandum for Brooks Campus #1, Establishing Its First Colocation Campus for the Underserved 2 MW-Plus Enterprise Market

$FNGRPress releaseNov 18, 2026, 9:15 AM ETRead the release

FingerMotion's subsidiary BlueFlare completed the Design Basis Memorandum for Brooks Campus #1, the company's first colocation campus, permitted for up to 9.9 MW in Alberta. The DBM is engineered to the requirements of a November 4 expression of interest for up to 7 MW of critical IT capacity via Cascadia Power, with parties negotiating toward binding agreements during a 30-day exclusivity period. If definitive agreements are reached, the arrangement is expected to generate more than $100 million in contracted revenue over an initial five-year term, with the first tranche targeted for service six months after signing.

Key figures

Target pue
1.2
Program sites
10
Revenue term years
5
Loiette capacity mw
7
Full capacity months
12-14
Permitted capacity mw
9.9
Expansion nameplate mw
19.2
Installed generation mw
9.6
Alberta program total mw
99
Primary market vacancy pct
1.4%
Target critical it capacity mw
7.2
Potential contracted revenue USD
100 million
Preleased under construction pct
80%+
First tranche months after binding
6