Cowboy State Mine Prefeasibility Study Delivers NPV Uplift and Maiden Ore Reserve

$ARRPress releaseNov 19, 2026, 10:11 AM ETRead the release

American Rare Earths' prefeasibility study for Cowboy State Mine delivers an after-tax NPV of approximately US$1.3B at an 8% real discount rate and 24% IRR, up from US$1.07B and 21% in the 2026 Scoping Study. The company declared a maiden Probable Ore Reserve of 116.4 Mt at 1,257 ppm PREO, supporting a 4.5 Mtpa open-pit operation over 26 years producing roughly 2,500 tonnes of NdPr oxide annually, with pre-production capital cut to US$840M including 15% contingency.

Key figures

Throughput
4.5 Mtpa
After tax irr
24%
Ndpr recovery
58.2%
Payback years
6.4
Mine life years
26
After tax npv 8pct
US$1.3 billion
Feasibility budget
approximately US$10 million
After tax npv 10pct
US$966 million
Npv uplift vs scoping
US$1.07B to US$1.3B at 8% real
Overall recovery preo
49.9%
Pre production capital
US$840M
Life of project capital
US$873M
Probable ore reserve tonnes
116.4 million tonnes at 1,257 ppm PREO
Annual ndpr oxide production
approximately 2,500 tonnes