GoldMining Announces Positive PEA Highlighting $532 Million After-Tax NPV and 42% IRR at its São Jorge Project, Brazil
GoldMining released a positive Preliminary Economic Assessment for its São Jorge Project in Brazil, highlighting a base-case after-tax NPV of $532 million and a 42.4% IRR. The project requires an initial capital investment of $202 million, yielding a highly efficient 2.6x NPV-to-capital ratio and a rapid 2.8-year payback period.
Key figures
- Aisc per oz
- 1464
- Total capex
- 267200000
- Initial capex
- 202200000
- Payback years
- 2.83
- Mine life years
- 10.6
- Sustaining capex
- 53000000
- Cash and securities
- 183000000
- Lo m gold production
- 543200
- Irr after tax base case
- 42.4%
- Npv after tax base case
- 532500000
- Irr after tax spot price
- 58.6%
- Npv after tax spot price
- 836800000
- Avg annual gold production
- 51250