Lithium Ionic Initiates Long-Lead Order and Provides Community Engagement Update

$LTHPress releaseJun 11, 2026, 7:00 AM ETRead the release

Lithium Ionic placed its first long-lead equipment order for the Bandeira Lithium Project, securing the main substation power transformer from Brazilian manufacturer Blutrafos. Overall project engineering has advanced to approximately 65% completion since the September 2025 Feasibility Study, with 1,352 meters of geotechnical drilling completed to support detailed design.