Silvercorp Announces the Construction Plan and Schedule for the Development of the Chaarat ZAAV Project

$SVMPress releaseJun 22, 2026, 7:00 AM ETRead the release

Silvercorp announced a $196.3 million budget for the Chaarat ZAAV joint venture, which is 70% owned by Silvercorp, to develop the Tulkubash and Kyzyltash gold projects. The plan allocates $57.3 million for 2026 and $139 million for 2027, focusing on constructing a 4 million tonne-per-year open-pit heap leach operation at Tulkubash and advancing studies for Kyzyltash.

Key figures

Phase 1 cost
166300000
Phase 2 cost
30000000
Spending 2026
57300000
Spending 2027
139000000
Total budget usd
196300000
Drilling 2026 meters
50,000 to 60,000
Drilling 2027 meters
60000
Ownership interest pct
70