Americas Gold and Silver Completes Phase 2 of No. 3 Shaft Upgrades at Galena, Increasing Current Hoisting Capacity by 100% and Provides Operations Update
Americas Gold and Silver completed Phase 2 of the No. 3 Shaft modernization at the Galena Complex, increasing regular hoisting capacity to 85 stph, representing more than a 100% increase over historical performance. The $1.1 million project enables a total hoisting capacity of 1,350 tons per day and supports a planned 50% increase in ore production rates to approximately 650 tons per day by the end of 2026.
Key figures
- Phase2 capex
- US$1.1 million
- Peak hoisting rate stph
- 105
- Hoist power increase pct
- 29
- Skip payload increase pct
- 40
- Regular hoisting rate stph
- 85
- Total hoisting capacity tpd
- 1350
- Historical hoisting rate stph
- 42
- Planned ore production rate tpd
- 650