The Metals Royalty Company Provides Update on Mesabi Metallics Construction Progress Following Executive Site Visit
The Mesabi Metallics project is 95.5% complete overall, with engineering at 99% and procurement at 99.3%, putting commissioning on track for July/August 2026. TMCR's CEO Brian Paes-Braga visited the site and confirmed confidence in the timeline, noting mechanical completions are being achieved across the facility.
Key figures
- Mine life years
- 23+
- Total investment usd
- $2.5 billion
- Project completion percent
- 95.5
- Engineering completion percent
- 99
- Procurement completion percent
- 99.3
- Construction completion percent
- 91.4