The Metals Royalty Company Provides Update on Mesabi Metallics Construction Progress Following Executive Site Visit

$TMCPress releaseJun 30, 2026, 7:30 AM ETRead the release

The Mesabi Metallics project is 95.5% complete overall, with engineering at 99% and procurement at 99.3%, putting commissioning on track for July/August 2026. TMCR's CEO Brian Paes-Braga visited the site and confirmed confidence in the timeline, noting mechanical completions are being achieved across the facility.

Key figures

Mine life years
23+
Total investment usd
$2.5 billion
Project completion percent
95.5
Engineering completion percent
99
Procurement completion percent
99.3
Construction completion percent
91.4