Hudbay Minerals received approval from Peru's SENACE to increase the mill processing capacity at its Constancia mine to 34 million tonnes per annum from 31 million tonnes. The amendment, the fifth for Constancia, extends the operational life of the mine and authorizes new infrastructure for tailings and water management.
Key figures
- New capacity mtpa
- 34 million
- Ore processed 2024
- 31.9 million tonnes
- Ore processed 2025
- 30.3 million tonnes
- Previous capacity mtpa
- 31 million
- Regulatory flexibility
- 10%