Fervo Energy Learning Curve Continues on 3rd Generation Well Design, Boosting Drilling Rates by 143% Since Its First Cape Station Well
Fervo Energy completed drilling of Sawtooth 7, the ninth well at Cape Station Phase II, reaching a total depth of 19,448 feet in just 21 days. The 3.0 well design achieved this pace despite being substantially deeper and hotter than previous designs, resulting in a 143% boost in drilling rates compared to the first Cape Station well.
Key figures
- Drilling time days
- 21
- Lateral length feet
- 7500
- Measured depth feet
- 19448
- Phase ii capacity mw
- 400
- Temperature fahrenheit
- 460
- Long term cost goal per kw
- 3000
- Phase ii cost target per kw
- 5500