Soluna Announces Monthly Business Update

$SLNHPress releaseJul 14, 2026, 7:30 AM ETRead the release

Soluna reported steady operations across its existing sites during June, noting full capacity at Dorothy 1A, 1B, 2, and Sophie despite increased grid curtailments. The company advanced its pipeline with substantial completion of a 9 MW phase at Project Kati 1 and the signing of an LOI for a potential tenant at the 350+ MW Project Kati 2.

Key figures

Project kati 1 mw
83
Project kati 2 mw
350
Project sophie mw
25
Project kati 1b mw
35
Briscoe wind farm mw
150
Project dorothy 2 mw
48
Project dorothy 3 mw
300
Project dorothy 1a mw
25
Project dorothy 1b mw
25
Project kati 1a galaxy mw
48
Project kati 1b soluna mdcs phase 2 mw
9
Project kati 1b soluna mdcs phase 3 mw
14

AI analysis

Red flags1 · Pro

The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.

AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.

    SLNH: Soluna Announces Monthly Business Update — AI Analysis | Signal8