Cerrado Gold Elects to Revise Timing for Completion of the Mont Sorcier Feasibility Study to Undertake Optimization Initiatives

$CERTPress releaseJul 15, 2026, 6:00 AM ETRead the release

Cerrado Gold has extended the completion date of the Bankable Feasibility Study for its Mont Sorcier iron project to incorporate optimization studies aimed at reducing capital and operating costs. The company will conduct a modest drill program in late Q3 2026 to upgrade inferred resources, which it expects will lower strip ratios, while the ESIA submission is now targeted for Q2 2027.

Key figures

Permit target date
year-end 2028
Drill program timing
late Q3
Esia submission date
Q2/27
Iron premium 67 vs 65
$20/t
Lagoa salgada interest
80%
Construction start date
end of Q1/2029
Property concession size
7,209-hectare