SunPower Completes Megawatt Millenium Solar Project

$SPWRPress releaseJul 20, 2026, 8:00 AM ETRead the release

SunPower completed a 977-kilowatt solar system at the Millenium Project in Palm Desert, California, achieving a project Net Promoter Score of 90. The system is expected to generate over 1.6 million kWh annually under a 30-year performance commitment, according to project owner PearlX. CEO T.J.

Key figures

Nps score
90
Old nps q2 25
-25
System size kw
977
Commitment years
30
Nps target q2 27
70%-plus
Payback period years
7.3
Annual generation kwh
over 1.6 million
Ca penetration percent
15
Us penetration percent
7
California solar cost per watt
2.47