Namib Minerals Sets Out Development Timelines and Milestones for Redwing Mine; Technical Programme of the Definitive Feasibility Study Fully Funded Through to Completion

$NAMMPress releaseJul 20, 2026, 4:15 PM ETRead the release

Namib Minerals outlined a five-step pathway to restart the Redwing Mine, targeting the completion of a fully funded Definitive Feasibility Study in early Q1 2027. The technical programme funding was secured via a $5.0 million non-dilutive term facility obtained by subsidiary Bulawayo Mining Company from Ecobank Zimbabwe for works at How Mine, freeing up internal cash flow.

Key figures

Guidance
DFS completion expected in early Q1 2027; Dewatering completion expected in Q4 2026
Deal Value Usd
5000000
Dfs completion
early Q1 2027
Dewatering completion
Q4 2026
Resource definition conclusion
Q4 2027