NextSource Materials Announces Updated Feasibility Study Results for Molo Mine Expansion to 150k tpa of SuperFlake(R) Graphite Concentrate

$NEXTPress releaseJul 27, 2026, 7:00 AM ETRead the release

NextSource Materials released an updated Feasibility Study for the Phase 2 expansion of its Molo Graphite Mine, targeting 150,000 tonnes per annum capacity over a 37-year life of mine. The study estimates a post-tax NPV of $348.4 million and a 20% IRR, with total capex of $290.8 million, utilizing a modular construction approach to mitigate risks.

Key figures

Capex usd
290800000
Pre tax npv usd
402500000
Post tax npv usd
348400000
Life of mine years
37
Pre tax irr percent
21.0%
Payback period years
7.2
Post tax irr percent
20.0%
Production capacity tpa
150000
Total cash cost fob usd per tonne
650
Average basket price usd per tonne
1138
All in sustaining cost usd per tonne
665