Surge Copper Files NI 43-101 Technical Report for the Berg PFS

$SURGPress releaseJul 30, 2026, 7:00 AM ETRead the release

Surge Copper filed the NI 43-101 Technical Report supporting the Pre-Feasibility Study for its Berg Copper Project in British Columbia. The report confirms strong base-case economics including an after-tax NPV of C$4.6 billion, a 24% IRR and a 2.9-year payback period based on a 28-year mine life.

Key figures

Mine life
28 years
Gold grade
0.02 g/t
Copper grade
0.22%
Silver grade
4.1 g/t
After tax irr
24%
Initial capex
C$4.7 billion
Payback period
2.9 years
Avg c1 cash cost
US$1.95/lb
Mineral reserves
1.2 billion tonnes
Molybdenum grade
0.026%
Processing capacity
120,000 tonne-per-day
Lom copper production
4.9 billion pounds
Lom silver production
89 million ounces
After tax npv 8 percent
C$4.6 billion
Lom molybdenum production
602 million pounds