NextDecade Provides Second Quarter 2026 Business Update

$NEXTPress releaseJul 30, 2026, 7:30 AM ETRead the release

NextDecade reported construction at the Rio Grande LNG facility is ahead of schedule and within budget, with Trains 1 and 2 reaching 74% overall completion as of June 2026. The company strengthened its financial position by closing a $1.0 billion term loan and a $3.5 billion senior secured notes offering, using proceeds to repay credit facilities and reduce outstanding borrowings.

Key figures

Term loan value
$1.0 billion
Phase 1 capacity
30 MTPA
Train 3 completion
50.4%
Train 4 completion
15.5%
Train 5 completion
9.4%
Senior notes offering
$3.5 billion
Trains 1 2 completion
74.0%
Swap settlement receipts
$109 million
Train 5 notes outstanding
$350 million