Stronger Grid Ahead: Power Line Rebuild to Boost Reliability in Northwest Ohio

$FEPress releaseApr 21, 2026, 1:28 PM ETRead the release

FirstEnergy Transmission is rebuilding 11 miles of high-voltage power line in Williams County, Ohio, through a $24 million initiative designed to enhance grid resilience and reduce outage risks for Toledo Edison customers. The West Unity (Stryker) 69-kV Line Rebuild Project involves replacing aging wooden poles with steel structures and higher-capacity wire to better withstand severe weather and support regional growth.

Key figures

Project cost USD
24 million
Power line length miles
11
FY 2026 2030 investment USD
36 billion
Northwest ohio investment USD
200 million
Transmission outage reduction pct
31