Sierra Madre Onsite Power Generation Fully Functional at La Guitarra

$SMPress releaseSep 10, 2026, 7:00 AM ETRead the release

Sierra Madre has commissioned twin 1,500-kW backup diesel generators at its producing La Guitarra silver-gold complex in Mexico, with the generators, substation, and machine control center all testing at manufacturer design levels. The facility lost 278 hours of production between January and August due to grid power interruptions — over 11 days — and management says the backup capacity, part of an aggressive cost-reduction program, should put lost production revenue and downtime costs behind the company.

Key figures

Stock options granted
350,000
Stock option term years
5
Marketing agreement fee USD
250,000
Stock option exercise price
$1.56
Downtime days lost production
11
Marketing agreement term months
2
Guitarra processing capacity tpd
500
Backup generator capacity kw each
1500
Grid outage downtime hours jan aug
278
Coloso nazareno backup generator kw
1250