Integra Resources Corp. (ITRG) Form 6-K — Oct 13, 2026

$ITRGForm 6-KFiled Oct 13, 2026, 3:03 PM ET0001062993-26-005300Original filing

Integra Resources provided a DeLamar Gold-Silver Project update showing detailed engineering, permitting, procurement and site-repair work advancing in line with plan since the December 2025 Feasibility Study. The company hired GenCap Mining Advisory as project financing advisor to evaluate capital alternatives ahead of a potential Final Investment Decision, which is expected after publication of the EIS and Record of Decision in the second half of 2027. The Feasibility Study outlined ~119,000 gold-equivalent ounces annual production in years 1-5 at US$389 million initial capital, with 46% after-tax IRR and US$774 million after-tax NPV at $3,000/oz gold.

Key figures

Eis rod expected
second half of 2027
Power capacity target
~6 MW by 2030
Mine plan boundary acres
13,425 acres
Feasibility after tax irr
46%
Pilot plant tons processed
~39,000 tons
Feasibility after tax npv usd
US$774 million
Feasibility initial capital usd
US$389 million
Avg gold equivalent oz years 1 5
~119,000 oz/year
Avg gold equivalent oz life of mine
106,000 oz/year