Net Power Inc. (NPWR) Form 8-K — Oct 22, 2026

$NPWRForm 8-KItems 1.01, 9.01Filed Oct 22, 2026, 4:10 PM ET0001104659-26-118155Original filing

Net Power extended the deadline to deliver the full notice to proceed and Mobilization Payment under its EPC Agreement with Saulsbury Industries from October 15, 2026 to March 31, 2027. The extension is conditional: Net Power and Saulsbury must execute the Fourth Amendment and a limited notice to proceed, with required payments, by November 15, 2026. If that fails, a $3.5 million termination payment becomes due on demand, and missing the March 31, 2027 deadline could allow termination of the EPC Agreement entirely.

Key figures

Fntp Deadline
March 31, 2027
Warrant Strike Price
11.5
Termination Payment Usd
3500000
Interim Milestone Deadline
November 15, 2026
Termination payment trigger
payable within 10 days of demand if Fourth Amendment and LNTP not executed by November 15, 2026
Mobilization payment deadline extended from
October 15, 2026