Allied Gold Corp (AAUC) Form 6-K — Sep 17, 2026

$AAUCForm 6-KFiled Sep 17, 2026, 5:05 PM ET0001171843-26-006097Original filing

Allied Gold Corporation reported that its Kurmuk Mine in Ethiopia has been connected to the national electrical grid and has fed first ore through the crushing circuit as the project completes commissioning and transitions toward operations. The 88-kilometre, 132-kV power line built by Ethiopian Electric Power supplies grid power at a fixed rate of approximately US$0.04 per kilowatt-hour under a 20-year power purchase agreement, supporting expected low production costs. First ore to the grinding circuit is expected in the coming weeks, with first gold to follow soon thereafter.

Key figures

Land package sq km
1450
Power line length km
88
Power line voltage kv
132
Grid power rate USD per kwh
approximately 0.04
Proven probable reserves oz
2.7 million
Current ore stockpile tonnes
approximately 1,000,000
Planned ore stockpile tonnes
nearly 1,500,000 (three months of ore feed)
Initial target mine life years
15
Year two production guidance oz
approximately 300,000
Power purchase agreement term years
20
Mine life avg production oz per year
at least 240,000
First full year production guidance oz
240,000-270,000
First four years avg production oz per year
approximately 290,000