Osisko Gold Group Inc. (ODV) Form 6-K — Oct 27, 2026
Osisko Gold Group (NYSE/TSXV: OGG) reported a construction update on its 100%-owned Cariboo Gold Project, which remains on schedule for first gold pour in Q1 2029 and commercial production in H2 2029. Overall project completion is estimated at approximately 28%, based on $355 million CAD in cumulative costs incurred through September 30, 2026. The estimated remaining cost to complete construction is approximately $907 million CAD. Detailed engineering is roughly 42% complete, over 50% of procurement packages have been awarded (~$360 million CAD committed), and key milestones include Valley Portal earthworks at 85% and the BL waste rock storage facility at 95%.
Key figures
- Trifr ytd 2026
- 1.05
- First gold pour
- Q1 2029
- Drill rigs active
- 16
- On site workforce
- over 400 active personnel
- Trif R person hours
- 1020000
- Cumulative costs cad
- $355 million
- Commercial production
- H2 2029
- Project completion pct
- 28
- Planned drilling meters
- 160000
- Regional drilling meters
- 50000
- Procurement commitments cad
- $360 million
- Procurement packages awarded
- over 50%
- Remaining cost to complete cad
- $907 million
- Costs incurred aug sep 2026 cad
- $84 million
- Mobile equipment fleet value cad
- $43 million
- Detailed engineering complete pct
- 42
- Underground development completed km
- 3.4
- Targeted advance rate meters per month
- 360