Osisko Gold Group Inc. (ODV) Form 6-K — Oct 27, 2026

$ODVForm 6-KFiled Oct 27, 2026, 7:00 AM ET0001171843-26-006836Original filing

Osisko Gold Group (NYSE/TSXV: OGG) reported a construction update on its 100%-owned Cariboo Gold Project, which remains on schedule for first gold pour in Q1 2029 and commercial production in H2 2029. Overall project completion is estimated at approximately 28%, based on $355 million CAD in cumulative costs incurred through September 30, 2026. The estimated remaining cost to complete construction is approximately $907 million CAD. Detailed engineering is roughly 42% complete, over 50% of procurement packages have been awarded (~$360 million CAD committed), and key milestones include Valley Portal earthworks at 85% and the BL waste rock storage facility at 95%.

Key figures

Trifr ytd 2026
1.05
First gold pour
Q1 2029
Drill rigs active
16
On site workforce
over 400 active personnel
Trif R person hours
1020000
Cumulative costs cad
$355 million
Commercial production
H2 2029
Project completion pct
28
Planned drilling meters
160000
Regional drilling meters
50000
Procurement commitments cad
$360 million
Procurement packages awarded
over 50%
Remaining cost to complete cad
$907 million
Costs incurred aug sep 2026 cad
$84 million
Mobile equipment fleet value cad
$43 million
Detailed engineering complete pct
42
Underground development completed km
3.4
Targeted advance rate meters per month
360