LITHIUM AMERICAS CORP. (LAC) Form 8-K — Aug 13, 2026

$LACForm 8-KItems 2.02, 7.01, 9.01Filed Aug 13, 2026, 6:55 AM ET0001193125-26-347834Original filing

Lithium Americas reported Q2 2026 net income of $1.7 million, a swing from a $13.2 million loss a year earlier, with no revenue as the company remains pre-production ahead of Thacker Pass startup. The company held approximately $1.3 billion in total cash and restricted cash at June 30, 2026, including $530.3 million at the Thacker Pass joint venture level. Construction at Thacker Pass in Nevada remains on schedule, with mechanical completion targeted for late 2027.

Key figures

EPS
$0.01 basic / $(0.02) diluted attributable to common stockholders in Q2 2026 (vs. $(0.06) in Q2 2025)
Guidance
FY2026 Capex guidance of $1.3-$1.6 billion for Thacker Pass Phase 1 maintained; mechanical completion targeted late 2027; power energization on track for Q4 2026
Net income
$1.7 million in Q2 2026 ($2.2 million attributable to LAC stockholders) vs. net loss of $13.2 million in Q2 2025
Total assets
$3,535.9 million at June 30, 2026
Cash position
$1,279.2 million cash and restricted cash at June 30, 2026 (approximately $1.3 billion, including $530.3 million at the Thacker Pass JV level)
Shares outstanding
363,042,943
Safety
3.42 million workhours without serious injury or lost-time incident; TRIR 0.58
Workforce
1,600+ on site, expected to exceed 2,000 in H2 2026
ATM program
$250 million March 2026 ATM; $68.5 million net proceeds YTD (13.0 million shares at avg $5.36) plus $4.2 million subsequent (1.1 million shares at avg $3.87)
Q2 2026 capex
$507.9 million (three months); $802.4 million (six months)
Phase1 capacity
40,000 tonnes per year battery-quality lithium carbonate
Total liabilities
$1,586.3 million at June 30, 2026 vs. $992.4 million at December 31, 2025
H1 2026 net income
$6.3 million vs. $(24.8) million loss in H1 2025
Doe loan increase H1
$637.0 million (advances of $774.0 million plus $17.4 million interest, net of $157.2 million amortized deferred financing costs)
Total capex estimate
$2.93 billion per NI 43-101 Technical Report
Yorkville debentures
up to $175 million aggregate principal; $150 million at initial closing; $25 million optional subsequent
Doe loan third advance
$342 million received June 3, 2026
Thacker pass ownership
LAC 62% / General Motors 38%
Doe loan total facility
$2.23 billion
Engineering procurement
detailed engineering >95% complete; procurement >80%
Tariff exposure estimate
$80-$100 million, majority expected in 2026, not included in $2.93 billion capex estimate
Cumulative capitalized costs
$1.8 billion ($1,785.1 million), of which $1.6 billion is within the total Capex estimate
Doe loan cumulative advances
$1.209 billion

Price after filing

1 day: +4.0%7 days: -8.6%30 days: -10.5%

Close on the filing date to close N calendar days later (from $3.25). Historical, not a forecast.

AI analysis

Red flags7 · Pro

The rest of the AI analysis, red flags and sentiment are part of Signal8 Pro.

AI-generated analysis of a public disclosure. Not investment advice; verify against the original document.

    LITHIUM AMERICAS CORP. (LAC) Form 8-K — Aug 13, 2026: AI Analysis | Signal8