Cameco filed the 2026 technical report for its McArthur River uranium operation, estimating a pre-tax NPV of $5.86 billion (8% discount rate) for its 69.805% share of current mineral reserves, with a pre-tax IRR of 11.9%. The report plans life-of-mine production of roughly 247.5 million pounds U3O8 at about 15.3 million pounds per year from 2030 onward, assuming $70/lb uranium pricing. Capital and operating cost estimates rose significantly versus the 2018 report — mine-life opex rose from $14.97 to $24.03 per pound and MRJV capital to $2.11 billion — reflecting aging infrastructure refresh, inflation in labour and materials, and added production flexibility.

Key figures

Pre Tax IRR
11.9%
Pre Tax Npv 8pct
$5.86 billion (Cdn) — Cameco's share of McArthur River reserves
Ytd2026 Production
10.5M lbs mined / 9.9M lbs packaged U3O8
Cameco MRJVOwnership
69.805%
Total Pre Tax Cash Flow
$12,100.0 million (Cdn, Cameco share)
Mine Development Capex
$622.3 million
Avg Operating Cost Per Lb
$24.03 U3O8 (vs $14.97 in 2018 report)
Uranium Price Assumption
$70 US/lb
Cameco Share Capital Costs
$1.47 billion
Total Life Of Mine Production
247,461 thousand lbs U3O8
Life Of Mine Capital Costs MRJV
$2.11 billion