$BTDRForm 6-KFiled Sep 2, 2026, 6:17 AM ET0001213900-26-096425Original filing

Bitdeer Technologies Group (NASDAQ: BTDR) announced it has completed the fee simple acquisition of approximately 200 acres of greenfield land in Milam County, Texas for total consideration of approximately $100 million, paid in cash. The parcel sits near the company's existing Rockdale facility, located about 70 miles from Austin. The Milam County sites currently feature approximately 563 MW of interconnected grid capacity, with existing plans expected to scale to 742 MW, plus a dedicated water supply. Outright ownership removes lease renewal risk and gives Bitdeer the long-term site control it says is required to develop and finance AI/HPC data center infrastructure.

Key figures

Deal value USD
100 million
Payment form
cash
Acres acquired
200
Global power capacity
3.0 GW
Distance to austin miles
70
Planned grid capacity mw
742
Total milam county acres
255
Existing grid capacity mw
563